FMP Timing Plan

FMP Timing Plan

Timings for the project are based on a completion date of 22 June, this allows a nine-week period for subsequent critical evaluation and write-up before an assignment submission date of 24 August.

Identification and development of the concept, image design, and asset procurement are the critical factors for the project – those factors upon whose completion all other tasks depend.

Float days are built into the timing plan to allow for contingencies, for example, illness, for reshoots, and to allow for critical evaluation.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.